Delays Expected, Caution Suggested as Lane Closure Set to Begin on Interstate 79 North of Bridgeport

By Connect-Bridgeport Staff on November 21, 2018 via Connect-Bridgeport.com

FROM THE WEST VIRGINIA DIVISION OF HIGHWAYS

Lane Closure One
 
The West Virginia Division of Highways advises motorists that there will be a Lane Closure on Interstate 79 from the West Virginia-Pennsylvania State Line to Mile Post 155.50 beginning on Monday, Nov. 26, 2018 at 3 a.m. through Saturday, Dec. 01, 2018 at 3 a.m. (24/hr).
 
The purpose for the closure is for road repair and paving.  Work will be performed on Interstate 79 Southbound Outside Lane (slow lane).  The Southbound Inside Lane (fast lane) will be open at this time.  A Lane Closure will be in place for the duration of this phase of work.  Expect delays. 
 
Motorists are advised to plan ahead and allow additional time for their commute.  Please note that inclement weather or unforeseen circumstances could change the project schedule. 
 
 
Lane Closure Two
 
The West Virginia Division of Highways advises motorists that there will be a Lane Closure on Interstate 79 from Mile Post 155.50 to the West Virginia-Pennsylvania State Line beginning on Monday, Nov. 26, 2018 at 3 a.m. through Saturday, Dec. 01, 2018 at 3 a.m. (24/hr).
 
The purpose for the closure is for road repair and paving.  Work will be performed on Interstate 79 Northbound Inside Lane (fast lane).  The Northbound Outside Lane (slow lane) will be open at this time.  A Lane Closure will be in place for the duration of this phase of work.  Expect delays. 
 
Motorists are advised to plan ahead and allow additional time for their commute.  Please note that inclement weather or unforeseen circumstances could change the project schedule. 
 